Brooklyn Bridge Park Updated & Fully Revealed

New, 24 comments


[Renderings courtesy of Michael Van Valkenburgh Associates]

Here is a big new set of renderings of Brooklyn Bridge Park, some of which have been trickling out for the last week or so and some of which haven't been seen before. In any case, it's been quite a while since new renderings were released. Land clearance for the park is underway and two sections (at Pier One and Pier Six, at opposite ends at Fulton Ferry Landing and Atlantic Avenue) are supposed to be finished late next year. Entire park will stretch for 1.3 miles. The original budget was $150 million, but it has climbed to $300 million, with the trouble being that only $225 million is funded. The Brooklyn Bridge Park Development Corp. estimates that about 2/3 of the park will be done by 2012.